CATLINS LANE, EASTCOTE
Start date: 3 January 2024
End date: 3 May 2024
Project manager: Sanjeev Pathak
Local delivery partner: Stanmore Quality Surfacing Ltd
Project overview
We are upgrading the gas pipes along Catlins Lane to ensure you continue to receive a reliable gas supply for many more years to come. Our aim is to replace all the metallic mains and service pipes in these locations. This means that we will need to excavate holes in the ground to access the gas pipes in order to inspect and replace them.
Due to the nature of the work involved, we have planned to deliver it in a number of phases to maximise efficiency and minimise disruption.
Contacting us
You can contact our customer care centre by telephone on 0800 085 4478 (lines are open 8.00am to 8.00pm Monday to Friday and 9.00am to 4.00pm on Saturdays) or by email to CustomerCareLondon@cadentgas.com.