Ferry road, hullbridge

 

Start date: 1 April

Duration: 11 weeks

Project manager: Stuart Griffiths

Local delivery partner: Forefront Utilities

 

Project overview

We are upgrading the gas pipes along Ferry Road to ensure you continue to receive a reliable gas supply for many more years to come. Our aim is to replace all the metallic mains and service pipes in these locations. This means that we will need to excavate holes in the ground to access the gas pipes in order to inspect and replace them.

Due to the nature of the work involved, we have planned to deliver it in a number of phases to maximise efficiency and minimise disruption.

Project phases

Phase 1: Two-way lights will be in place on Ferry Road at the junctions of Waxwell Road, Oakleigh Avenue. The junction with Abbey Road will be closed.

Phase 2: Two-way lights will be in place on Ferry Road at the junctions of Waxwell Road, Oakleigh Avenue. The junction with Abbey Road will be closed.

Phase 3: Two-way lights will be in place on Ferry Road at the junctions of Oakleigh Avenue. The junction with Abbey Road will be closed.

Phase 4: Two-way lights will be in place on Ferry Road with junctions of Oakleigh Avenue. The junction with Abbey Road will be closed.

Phase 5: Two-way lights will be in place on Ferry Road and the junction of High Elms will be closed.

Phase 6: Two-way lights will be in place on Ferry Road and the junction South Avenue will be closed.

Phase 7: Two-way lights on Ferry Road and the junction of South Avenue will be closed.

Contacting us

You can contact our customer care centre by telephone on 0800 085 4478 (lines are open 8.00am to 8.00pm Monday to Friday and 9.00am to 4.00pm on Saturdays) or by email to CustomerCareLondon@cadentgas.com


Project updates