headstone lane, harrow

 

Start date: 7 March 2022

Duration: 28 weeks

Project manager: Trevor Trent

Local delivery partner: KLT Utilities

 

Project overview

We are upgrading the gas pipes along Headstone Lane to ensure you continue to receive a reliable gas supply for many more years to come. Our aim is to replace all the metallic mains and service pipes in these locations. This means that we will need to excavate holes in the ground to access the gas pipes in order to inspect and replace them.

Due to the nature of the work involved, we have planned to deliver it in a number of phases to maximise efficiency and minimise disruption.

 

Project phases

Southbound lane – 13 weeks

Phase 1: 7 – 12 March

Replace approximately 150m of existing gas pipe from opposite the junction of Elmcroft Crescent to the junction of Holmdene Avenue. Two-way traffic lights will be in place along with road closures to side roads.

Phase 2: 14 – 19 March

Replace approximately 170m of existing gas pipe from the junction of Holmdene Avenue to the junction of Manor Park Drive. Two-way traffic lights will be in place along with road closures to side roads.

Phase 3: 21 March – 2 April

Replace approximately 140m of existing gas pipe from the junction of Parkfield Gardens to the junction of Almond Way. Two-way traffic lights will be in place along with road closures to side roads.

Phase 4: 4 - 23 April

Replace approximately 290m of existing gas pipe from the junction of Pinner Road to the junction of Elmcroft Crescent. The northbound carriageway will be closed during this time.

Phase 5: 25 - 30 April

Replace approximately 140m of existing gas pipe from the junction of Almond Way to 161 Headstone Lane. Two-way traffic lights will be in place along with road closures to side roads.

Phase 7: 2 - 14 May

Replace approximately 290m of existing gas pipe from 161 to 185 Headstone Lane. Two-way traffic lights will be in place along with road closures to side roads.

Phase 8: 16 - 21 May

Replace approximately 110m of existing gas pipe from 185 Headstone Lane to the junction of Fernleigh Court. Three-way traffic lights will be in place along with road closures to side roads.

Phase 9: 25 May – 4 June

Replace approximately 120m of existing gas pipe from the junction of Fernleigh Court to the railway bridge. Two-way traffic lights will be in place along with road closures to side roads.

 

Northbound lane – 18 weeks

Phase 10: 6 - 18 June

Replace approximately 150m of existing gas pipe from the junction of Fernleigh Court to 230 Headstone Lane. Two-way traffic lights will be in place along with road closures to side roads.

Phase 11: 20 June – 2 July

Replace approximately 130m of existing gas pipe from 230 to 196 Headstone Lane. Two-way traffic lights will be in place along with road closures to side roads.

Phase 12: 4 -16 July

Replace approximately 150m of existing gas pipe from 196 to 166 Headstone Lane. Two-way traffic lights will be in place along with road closures to side roads.

Phase 13: 18 - 23 July

Replace approximately 140m of existing gas pipe from 166 Headstone Lane to the junction of Parkfield Gardens. Two-way traffic lights will be in place along with road closures to side roads.

Phase 14a: 25 July – 3 August

Replace approximately 180m of existing gas pipe southbound on Headstone Lane from the junction of Manor Park Drive to the junction of Parkfield Gardens. Two-way traffic lights will be in place along with road closures to side roads.

Phase 14b: 4 – 13 August

Replace approximately 170m of existing gas pipe Northbound on Headstone Lane from the junction of Parkfield Gardens to the junction of Manor Park Drive. Two-way traffic lights will be in place along with road closures to side roads.

Phase 15: 15 August – 3 September

Replace approximately 130m of existing gas pipe from the junction of Manor Way to Pinner Road. Four-way traffic lights will be in place.

Phase 16: 5 – 10 September

Replace approximately 150m of existing gas pipe from the junction of Manor Park Drive to 100 Headstone Lane. Two-way traffic lights will be in place along with road closures to side roads.

Phase 17: 12 – 24 September

Replace approximately 170m of existing gas pipe from 100 Headstone Lane to junction of Elmcroft Crescent. Two-way traffic lights will be in place along with road closures to side roads.

Phase 18: 26 September – 1 October

Replace approximately 130m of existing gas pipe from the junction of Elmcroft Crescent to junction of Hillview Gardens. Two-way traffic lights will be in place along with road closures to side roads.

Phase 19: 3 – 8 October

Replace approximately 125m of existing gas pipe from the junction of Hillview Gardens to the junction of Manor Way. Two-way traffic lights will be in place along with road closures to side roads.

 