london Road, purfleet
Start date: 1 April 2024
Duration: 30 weeks
Project manager: Christopher McVeigh
Local delivery partner: Terrafirma Pipeline Ltd
Project overview
We are upgrading the gas pipes along London Road to ensure you continue to receive a reliable gas supply for many more years to come. Our aim is to replace all the metallic mains and service pipes in these locations. This means that we will need to excavate holes in the ground to access the gas pipes in order to inspect and replace them.
Due to the nature of the work involved, we have planned to deliver it in a number of phases to maximise efficiency and minimise disruption.
Phase 1: 63m - 1.5 weeks
This phase will be completed under four-way temporary traffic lights.
Phase 2: 200m – 2 weeks
This phase will be completed under a temporary road closure, access will be maintained for residents and deliveries only.
Phase 3: 100m – 2 weeks
This phase will be completed under a temporary road closure, access will be maintained for residents and deliveries only.
Phase 4: 200m – 2 weeks
This phase will be completed under three-way temporary traffic lights.
Phase 5: 100m – 1.5 weeks
This phase will be completed under three-way temporary traffic lights.
Phase 6: 80m – 2 weeks
This phase will be completed under two-way temporary traffic lights.
Phase 7: 75m – 1 weeks
This phase will be completed under three-way temporary traffic lights.
Phase 8: 200m – 1 weeks
This phase will be completed under four-way temporary traffic lights.
Phase 9: 200m – 1 week
This phase will be completed under four-way temporary traffic lights.
Phase 10: 65m – 1.5 weeks
This phase will be completed under four-way temporary traffic lights.
Phase 11: 65m – 1 week
This phase will be completed under four-way temporary traffic lights.
Phase 12: 85m – 1.5 week
This phase will be completed under three-way temporary traffic lights.
Phase 13: 200m – 1.5 weeks
This phase will be completed under four-way temporary traffic lights.
Phase 14: 60m – 1 week
This phase will be completed under two-way temporary traffic lights.
Phase 15: 65m – 1 week
This phase will be completed under two-way temporary traffic lights.
Phase 16: 73m – 1 week
This phase will be completed under four-way temporary traffic lights.
Phase 17: 120m – 1 week
This phase will be completed under two-way temporary traffic lights.
Phase 18: 50m – 1 week
This phase will be completed under two-way temporary traffic lights.
Phase 19: 50m – 1 week
This phase will be completed under two-way temporary traffic lights.
Phase 20: 50m – 1 week
This phase will be completed under two-way temporary traffic lights.
Phase 21: 50m – 1 week
This phase will be completed under three-way temporary traffic lights.
Phase 22: 50m – 1 week
This phase will be completed under two-way temporary traffic lights.
Phase 23: 94m – 2 weeks
This phase will be completed under two-way temporary traffic lights.
Phase 24: 95m – 1.5 weeks
This phase will be completed under a temporary road closure, access will be maintained for residents and deliveries only.
Phase 25: 100m –1.5 weeks
This phase will be completed under a temporary road closure, access will be maintained for residents and deliveries only.
Phase 26: 80m – 2 weeks
This phase will be completed under a temporary road closure, access will be maintained for residents and deliveries only.
Phase 27: 90m – 3 weeks
This phase will be completed under a temporary road closure, access will be maintained for residents and deliveries only.
Contacting us