london Road, purfleet

 

Start date: 1 April 2024

Duration: 30 weeks

Project manager: Christopher McVeigh

Local delivery partner: Terrafirma Pipeline Ltd

 

Project overview

We are upgrading the gas pipes along London Road to ensure you continue to receive a reliable gas supply for many more years to come. Our aim is to replace all the metallic mains and service pipes in these locations. This means that we will need to excavate holes in the ground to access the gas pipes in order to inspect and replace them.

Due to the nature of the work involved, we have planned to deliver it in a number of phases to maximise efficiency and minimise disruption.

 

Phase 1: 63m - 1.5 weeks

This phase will be completed under four-way temporary traffic lights.

Phase 2: 200m – 2 weeks

This phase will be completed under a temporary road closure, access will be maintained for residents and deliveries only.

Phase 3: 100m – 2 weeks

This phase will be completed under a temporary road closure, access will be maintained for residents and deliveries only.

Phase 4: 200m – 2 weeks

This phase will be completed under three-way temporary traffic lights.

Phase 5: 100m – 1.5 weeks

This phase will be completed under three-way temporary traffic lights.

 Phase 6: 80m – 2 weeks

This phase will be completed under two-way temporary traffic lights.

Phase 7: 75m – 1 weeks

This phase will be completed under three-way temporary traffic lights.

Phase 8: 200m – 1 weeks

This phase will be completed under four-way temporary traffic lights.

Phase 9: 200m – 1 week

This phase will be completed under four-way temporary traffic lights.

 

Phase 10: 65m – 1.5 weeks

This phase will be completed under four-way temporary traffic lights.

Phase 11: 65m – 1 week

This phase will be completed under four-way temporary traffic lights.

Phase 12: 85m – 1.5 week

This phase will be completed under three-way temporary traffic lights.

Phase 13: 200m – 1.5 weeks

This phase will be completed under four-way temporary traffic lights.

Phase 14: 60m – 1 week

This phase will be completed under two-way temporary traffic lights.

Phase 15: 65m – 1 week

This phase will be completed under two-way temporary traffic lights.

Phase 16: 73m – 1 week

This phase will be completed under four-way temporary traffic lights.

Phase 17: 120m – 1 week

This phase will be completed under two-way temporary traffic lights.

Phase 18: 50m – 1 week

This phase will be completed under two-way temporary traffic lights.

Phase 19: 50m – 1 week

This phase will be completed under two-way temporary traffic lights.

 

Phase 20: 50m – 1 week

This phase will be completed under two-way temporary traffic lights.

Phase 21: 50m – 1 week

This phase will be completed under three-way temporary traffic lights.

Phase 22: 50m – 1 week

This phase will be completed under two-way temporary traffic lights.

Phase 23: 94m – 2 weeks

This phase will be completed under two-way temporary traffic lights.

Phase 24: 95m – 1.5 weeks

This phase will be completed under a temporary road closure, access will be maintained for residents and deliveries only.

Phase 25: 100m –1.5 weeks

This phase will be completed under a temporary road closure, access will be maintained for residents and deliveries only.

Phase 26: 80m – 2 weeks

This phase will be completed under a temporary road closure, access will be maintained for residents and deliveries only.

 Phase 27: 90m – 3 weeks

This phase will be completed under a temporary road closure, access will be maintained for residents and deliveries only.

Contacting us

You can contact our customer care centre by telephone on 0800 085 4478 (lines are open 8.00am to 8.00pm Monday to Friday and 9.00am to 4.00pm on Saturdays) or by email to CustomerCareLondon@cadentgas.com